Project Spotlight: Rose Valley Wind Project
- Jul 10
- 3 min read
The Rose Valley Wind Project is a 200 MW wind facility now under construction near Assiniboia, Saskatchewan, majority-owned by M-Squared Renewables — an Indigenous development corporation representing the nine Nations of the Meadow Lake Tribal Council and Mistawasis Nêhiyawak First Nation. With M-Squared holding 51% ownership, Rose Valley carries the largest Indigenous ownership share of any wind project of its size in Saskatchewan.

Project Overview
Rose Valley Wind is comprised of 28 wind turbines in the Rural Municipality of Excel No. 71, supporting a power purchase agreement with SaskPower. The project was selected through SaskPower's 2024 Request for Proposals for new wind generation and reached financial close in mid-2026, with a sod-turning ceremony held June 15, 2026. Construction is expected to be complete by late 2027.
Project Details
Location: Rural Municipality of Excel No. 71, near Assiniboia, Saskatchewan
Technology: Onshore wind
Capacity: 200 MW
Status: Under construction; commercial operation expected late 2027
Industry Partner: Potentia Renewables Inc.
Indigenous Partner: M-Squared Renewables (Meadow Lake Tribal Council's nine Nations + Mistawasis Nêhiyawak First Nation)
Indigenous Ownership
M-Squared Renewables holds 51% ownership of Rose Valley Wind, making it the majority owner alongside developer Potentia Renewables. M-Squared is itself owned by ten First Nations — the nine Nations of the Meadow Lake Tribal Council and Mistawasis Nêhiyawak First Nation — giving each community a direct equity stake in project revenues rather than a fixed benefit payment.
"Through our partnerships, we are helping build Saskatchewan's energy future while advancing Indigenous ownership, economic reconciliation, and self-determination." Jeremy Norman, Tribal Chief, Meadow Lake Tribal Council
Funding Details
In June 2026, the Canada Infrastructure Bank (CIB) reached financial close with Potentia Renewables and M-Squared Renewables on a financing package for the project:
A $128 million project loan to Potentia Renewables and M-Squared Renewables
A $36.4 million Indigenous equity loan, enabling M-Squared's majority ownership position
A combined CIB financing package totalling $164.4 million
Senior lending support from Desjardins Group and KfW IPEX-Bank
Why This Project Matters
Rose Valley Wind is a useful benchmark for how Indigenous ownership structures in Canadian wind are evolving:
Majority, not minority, ownership. At 51%, M-Squared's stake exceeds the equity ranges typical of earlier-generation IPP partnerships, and SaskPower itself has flagged it as the largest Indigenous ownership share of any similarly sized wind project in the province.
Dedicated equity financing is the enabler. The CIB's separate Indigenous equity loan — distinct from the project loan — is the specific mechanism that allowed M-Squared to reach majority ownership without over-leveraging community balance sheets.
Multi-nation ownership vehicles are scaling. M-Squared pools the economic interests of ten First Nations into a single development corporation, a model likely to recur as more Tribal Councils pursue joint equity vehicles for large-scale generation assets.
Revenue flows to community priorities. MLTC leadership has indicated that distributions from prior holdings have funded housing, youth centres, and community infrastructure — with each Nation independently directing its share.
Indigenous Energy Ownership Tracker
Rose Valley Wind is one of the many Indigenous-owned power projects tracked in IEM's Indigenous Energy Ownership Tracker (IEOT). It was built to centralize project ownership details, identify partnership models, and improve transparency across Canada's energy transition.
🔗 Explore the IEOT: